NEXTDC has upgraded its FY27 guidance for net revenue and underlying EBITDA despite significant headwinds from delays in its M3 Melbourne expansion, signaling management’s confidence in the underlying demand for data centre capacity. Net revenue guidance has been increased to A$485 million to A$500 million from A$475 million to A$500 million, while underlying EBITDA guidance has been raised to A$260 million to A$275 million from A$245 million to A$265 million. This guidance excludes the affected customer contracts at M3, which were impacted by third-party power supply delays from Jemena.
The M3 delays stem from community concerns about power infrastructure installation in West Footscray, leading Jemena to suspend parts of its 66kV line augmentation works. NEXTDC is working with Jemena, local government, and the community on alternative power solutions, with Jemena advising the earliest restart of suspended works would be February 2027. The affected M3 capacity remains under contract, subject to customer rights, though the timing of these contributions to revenue remains uncertain. The company expects to provide updates on the M3 situation at its 1H27 results in February 2027.
Management has implemented significant capital discipline following a comprehensive review. FY27 capital expenditure guidance has been reaffirmed at A$4.5 billion to A$5 billion, representing a reduction of approximately A$980 million on a like-for-like basis compared to prior guidance. This tightening reflects a deliberate shift toward delivering the company’s forward order book of 565MW, the largest in NEXTDC’s history. All uncontracted development projects, including M4, M5, S5, S7, GC1, and AK1, have been placed on hold pending customer contracts with returns above the cost of capital and sufficient advancement of power and planning requirements.
Governance improvements are underway, with two new independent non-executive directors expected to be appointed in the first calendar quarter of 2027. Current chairman Douglas Flynn has indicated his intention to retire once a new chairman is appointed, while director Stuart Davis intends to step down once the board renewal process is complete. The company has also strengthened oversight of the M3 program through the appointment of board sponsors and established a new Sustainability Committee Charter with clear principles for community engagement.
A rules-based approach to leveraged ETFs
See how our quantitative strategy works and who it suits.
Explore the strategyBecome an authorised representative
Advise your clients under an established AFSL without building your own. Choose AR or CAR.
Become an AR or CARThe balance sheet remains robust with A$8.2 billion of available liquidity as at 31 October 2026, comprising A$793 million in cash and A$6.7 billion in undrawn senior debt facilities. The company has also benefited from opportunistic equity investment, with Ackland Investments, a joint venture between Goodman Group and Digital Realty, acquiring a 9.9 percent stake, showing third-party confidence in the value of NEXTDC’s asset base. Investors should monitor the February 2027 1H27 results for progress updates on the M3 power solution timeline and confirmation of which alternative power routes will be pursued. This announcement is price sensitive and has been flagged as material by the ASX.
View the full ASX announcement (PDF)
About NEXTDC Limited (ASX: NXT)
NEXTDC Limited develops and operates data centers in Australia and the Asia-Pacific region. The company offers data center colocation solutions, high-performance computing, disaster recovery services, and various digital infrastructure solutions to enterprise clients, government agencies, and cloud providers. Headquartered in Brisbane, Australia, NEXTDC provides critical connectivity and infrastructure services across its network of facilities.